|
The
San José-Caldera Highway Still Uncertain, Only A
Dream For Many
Three decades later, the construction of the new
highway that would reduce the trip between San
José and Caldera to in less than one hour
instead of the almost two hours it takes now, is
still ongoing and its completion is yet a
certainty.
The new road would mean a big boost to the
Central Pacific, cutting the travel time between
San José and the beaches of Jacó and Herradura
(Los Sueños) and the port of Caldera and
Puntarenas in less than one hour.
It appears that the lack of planning and the
constant changes by the Ministerio de Obras
Públicas y Transportes (MOPT) is turning the
highway into more than a dream that one day
the drive to the beach will be fast and on a
good road, instead of the current route known as
"el Monte Aguacate", a winding narrow road with
constant blind curves that can leave even the
best of drivers with their hair raised on end.
The dream began back in the 1970's when the
first lines were sketched out for a road that
has been under construction since and mired in
controversy as contract after contract has been
signed and contractor after contractor has
resigned from the job, never completing the work
from many reasons ranging from rising fuel costs
of late to poor or no planning on the part of
the Transport authorities and their constant
changes.
The road for many Costa Ricans is a tale from
childhood, when their parents spoke about the
road to the Pacific that would be modern and
take one there in record time.
The road would stretch for 77 kilometres cutting
through valleys and no need to climb the high
mountains of the area. The road would be build
in three sections: the 14.5 kilometres between
the La Sabana to Cuidad Colon, which is already
there save for the sections between Santa Ana
and Cuidad Colon where the road has to still be
widened; the 38 kiloemtres between Cuidad Colon
and Orotina, which has to be be newly
constructed: and the 24 kilometres between
Orotina and Caldera, which has to be
reconstructed.
So far, only the bridges between Cuidad Colon
and Orotina have been built for some time and
have become dilapidated and will soon need
repairs. The main bridge in the area known as La
Guacima has become a deal garbage dump, the
other bridges constructed more than five years
ago, have been left in a state of abandonment
and have been a haven for vandals.
Rumours of heavy machinery and work in progress
are constant, only to find that the latest
contractor moves in their equipment in the area
and then pulling it back due to contractual
dispute with government authorities.
Many visitors, especially those looking to
invest in the Central Pacific, get excited when
the hear the rumours as they imagine their
investments grow quickly, based on the promises
from the local real estate professionals.
The latest contractor, the Consorcio Autopistas
del Sol has 24 months to complete the work and
with us$160 million dollars in financing from
the Banco Centroamericano and us$50 million
dollars from the Caja de Madrid bank, it appears
that the dream may soon become a reality.
But wait, there is a snag in this latest round.
The financiers want some security assurances not
included in the original contract and the
Contraloría General de la Republica
(Comptroller's office) has yet, after months of
discussions, to give the green light to the
contract amendments, so the work is paralyzed
once again.
Rodolfo Silva was the minister under president
"Don Pepe" - José Maria Figueres Ferrer - when
the idea was first created.
Silva assures that taking away resources from
the Consejo Nacional de Vialidad (CONAVI) and
the constant legal obstacles has delayed the
project and subdued Silva's dream to one day
inaugurate the new road.
The current vice-ministro de Concesión, Luis
Diego vargas, promised a few months ago that the
work would again resume on the project would be
finished within two years.
We are still waiting. And dreaming of the day
when...
|
|

A view of
the current state of the dream highway
between San José and the Central
Pacific. The road has been in the
planning and construction stage for more
than 20 years and no clear end as to
when it will become a reality.
|
|
|
|
|
|