COSTA RICA

•  Find True Love in Costa Rica!

Sunday 03  May 2009, San José, Costa Rica  Home Contact Us Subscribe To Our Newsletter
First Case of Swine Flu in Costa Rica Confirmed By CDC
Costa Rican President Arias Wants To Know If Catholic Church Is Spending On The Poor
Prepare Yourself As Rainy Season Comes Early To San Jose
Security Firm Looking To Hire 50 People
Paving of Tilaran-Libano Route 35% Complete


Paving of Tilaran-Libano Route 35% Complete

Now that all dirt has been moved and foundation materials and drainage pipes have been installed along the 9.2 kilometers of the Libano-Tilaran road in Tilaran canton, officials estimate that progress on this paving project is at approximately 35 percent now.

The project includes a budget of 2.4 billion colones ($4.36 million), which will turn the dirt road into a two-lane asphalt highway. The original road has been expanded for that purpose.

The project will allow residents of the area and visitors to move around more quickly and safely and during the entire year, as inclement weather can make the current road impassable.

The works entail compaction of the dirt road, placing a gravel foundation of 25 centimeters, a concrete foundation of 20 centimeters, and an asphalt layer seven centimeters thick. Finally, the new road will be properly outfitted with horizontal and vertical signage.

Officials are also considering replacing some large concrete drainage pipes with bridges. Construction on this project began last December, and officials expect that paving will be taking place in about two months, with the entire project ready by July.

In other road improvement projects around Guanacaste, crews have finished putting a new asphalt layer and making other improvements to two sections of highway between the Pan American Highway North and the Puntarenas district of Guacimal (on the way to Monteverde). All in all, this project included 18.9 kilometers and had a total cost of 2.1 billion colones ($3.8 million).

This road has been outfitted with all horizontal and vertical signage, in addition to metal guardrails around dangerous curves and bridges. Additionally, soil was removed around the road to widen shoulders and reduce risks at some sharp curves.

The project was also divided into two sections. The first included 12 kilometers between the Pan American Highway North intersection and Los Angeles de Guacimal, where there was only a stabilized base road that served as foundation to the new asphalt layer, which was then installed in addition to new drainage and other works that should last at least 10 years.

The second section, 6.9 kilometers long, is between Los Angeles and Guacimal. There, the old gravel road was outfitted with drainage and covered with two asphalt lanes (in some parts of this road there was only one lane before). Part of the effort also entailed recovering some land to be able to properly expand the road. This project, too, is expected to have a 10-year useful lifespan.

Back in 2007, the Santa Elena-Monteverde (15.2 kilometers) section of this route had been paved, for an investment of 1.090 billion colones ($1.98 million at the current exchange rate).

Other road-improvement initiatives are underway in Guanacaste, whether for gravel roads or paved highways, including the Carrillo-Lajas route, which will cost 4.2 billion colones ($7.6 million) to complete.
 
 
 
 
 
 

 

 

2002 - 2009  INSIDECOSTARICA.COM.2133-1000 San José, Costa Rica 
E-Mail: editor@insidecostarica.com  Telephone: (506) 8845 5800  / (506) 2231 3205  Fax: (506) 2232 6337
For more information on this website contact: editor@insidecostarica.com 

Subscribe to our newsletter!